Construction Update 2010.04.23

From the water  10.04.22

Sandblasting finished down stairs, mechanical/electrical picking up, framing starting on the upper floor.  Shop drawings reviewed.  More photos after the jump.

Kitchen Framing
Kitchen framing started.  The open section in the centre will be the opening for demonstrations and teaching.

Bunk room

Two small bunkrooms being built into the haunch overhangs (think ship’s bunks. These will allow researchers who are out working late night tides to stay on site and not have to drive back to Nanaimo. Otherwise these will serve as small offices.

Outriggers

Steel outriggers are being mounted on the ends of the roof beams.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: